Q.1.
Rosa can eat 32 rosogollas in one hour. Her sister Lila needs three hours to eat the same number. How much time will they take to eat 32 rosogollas together ?
Q.2.
Two spinning machines A and B can together produce 300000 metres of cloth in 10 hours. If machine B alone can produce the same amount of cloth in 15 hours. Then how much cloth can machine A produce alone in 10 hours ?
Q.3.
X, Y and Z complete a work in 6 days. X or Y alone can do the same work in 16 days. In how many days Z alone can finish the same work ?
Q.4.
x does $$\frac{1}{4}$$ of a job in 6 days. y completes rest of the job in 12 days. Then x and y could complete the job together in = ?
Q.5.
Reena, Aastha and Shloka can independently complete a piece of work in 6 hours, 4 hours and 12 hours respectively. If they work together, how much time will they take to complete that piece of work ?
Q.6.
A can finish a work in 18 days and B can do the same work in half the time take by A. Then, working together, what part of the same work they can finish in a day ?
Q.7.
In two days A, B and C together can finish $$\frac{1}{2}$$ of a work and in another 2 days B and C together can finish $$\frac{3}{{10}}$$ part of the work. Then A alone can complete the whole work in ?
Q.8.
Amit and Sumit can plough a field in 4 days. Sumit alone can plough the field in 6 days. In how many days will Amit alone plough the feild ?
Q.9.
P can complete $$\frac{1}{4}$$ of a work in 10 days, Q can complete 40% of the same work in 145 days. R, complete $$\frac{1}{3}$$ of the work in 13 days and S, $$\frac{1}{6}$$ of the work in 7 days. Who will be able complete the work first ?
Q.10.
George takes 8 hours to copy a 50-page manuscript while Sonia can copy the same manuscript in 6 hours. How many hours would it take them to copy a 100-page manuscript, if they work together ?
Q.11.
A can complete a certain work in 4 minutes, B in 5 minutes, C in 6 minutes, D in 10 minutes and E in 12 minutes. The average number of units of work completed by them per minute will be = ?
Q.12.
A daily-wages labourer was engaged for a certain number of days for Rs. 5750, but being absent on some of those days he paid only Rs. 5000. What were his maximum possible daily wages ?
Q.13.
A and B together can do a piece of work in 8 days, B and C together in 10 days, while C and A together in 6 days, if they all work together the work will be completed in ?
Q.14.
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Q.15.
A and B can do a job together in 7 days. A is $$1\frac{3}{4}$$  times as efficient as B. The same job can be done by A alone in :
Q.16.
A and B together complete a piece of work in T days. If A alone completes the work in T + 3 days and B alone completes the piece of work in T + 12 days, what is T ?
Q.17.
Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?
Q.18.
A and B together can complete a piece of work in 8 days, B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone takes to complete the work ?
Q.19.
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
Q.20.
A can finish a piece of work in 18 days and B can do the same work in half of the time taken by A. Then working together what part of the same work they can finish in a day ?
Q.21.
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
Q.22.
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Q.23.
A and B completed a work together in 5 days. had A worked at twice the speed and B at half the speed, it would have taken them four days to complete the job. How much time would it take for A alone to do the work?
Q.24.
40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?
Q.25.
A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?
Q.26.
A and B can do a piece of work in 72 days, B and C can do it in 120 days and A and C can do it in 90 days. In how many days all three together can do the work ?
Q.27.
A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Q.28.
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
Q.29.
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
Q.30.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?