Q.1.
_________ is defined as the main plank which remains in contact with sides of Trench.
Q.2.
Identify the missing data in the below figure.
Questionconstruction-building-materials-questions-answers2.jpg
Q.3.
Identify the missing data in the below figure.
Questionconstruction-building-materials-questions-answers3.jpg
Q.4.
Identify the missing data.
Questionconstruction-building-materials-questions-answers4.jpg
Q.5.
Identify the given type of Timbering.
Questionconstruction-building-materials-questions-answers5.jpg
Q.6.
Identify the given type of Timbering.
Questionconstruction-building-materials-questions-answers6.jpg
Q.7.
The __________ arrangement of preventing the sleep of earth in foundation trenches is used when the excavation is to be carried out in the moderately firm ground.
Q.8.
The _______ arrangement of preventing the slip of earth in the foundation trenches is adopted when a large area is to be excavated for depth greater thanmeters.
Q.9.
In _______ arrangement, the vertical sheets are placed nearer or sometimes, touching each other.
Q.10.
The _______ method is similar to box sheeting except that the work is carried out in stages and at each stage, and offset is provided.