The process of rolling, folding and spreading of the particle is known as the __________ of concrete.
a) Curing
b) Mixing
c) Grouting
d) Watering
Q.2.
For _______ mixing, the materials are stacked on watertight platform, which may be either of wood, Brick or steel.
a) Machine
b) Roller
c) Hand
d) Mixer
Q.3.
For ________ mixing, all the material of concrete including water, are collected in a revolving drum and drummer is rotated for a certain period.
a) Drum
b) Hand
c) Roller
d) Machine
Q.4.
For ordinary building works, the ___________ is formed and the concrete is conveyed in pans from hand to hand.
a) Conveyor belt
b) Bucket
c) Human ladder
d) Pump
Q.5.
The term ________ of concrete is used to mean the compaction between aggregate and aggregate; between aggregate and reinforcement and between aggregate and forms.
a) Consolidation
b) Hardening
c) Compaction
d) Curing
Q.6.
The ________ are the gaps between two individual particles.
a) Spaces
b) Voids
c) Pores
d) Bubbles
Q.7.
Form unimportant works, the consolidation of concrete is carried out by ___________ method which include Ramming, tamping, spading and slicing with suitable tools.
a) Machine
b) Roller
c) Vibrator
d) Hand
Q.8.
_________ vibrators consists of the Steel Tube which is inserted in fresh concrete.
a) Surface vibrators
b) Internal vibrators
c) Vibrating table
d) Shutter vibrators
Q.9.
_________ vibrators are mounted on platforms or screeds.
a) Form vibrators
b) Surface vibrators
c) Shutter vibrators
d) Immersion vibrators
Q.10.
__________ vibrators are attached to the form work and the external centring of walls, column, etc.
a) Shutter vibrators
b) Surface vibrators
c) Internal vibrators
d) Immersion vibrators