MCQ Questions
Q.1.
The sequence of work for a job is also known as its
  • 0%
    finite planning
  • 0%
    input output control
  • 100%
    routing
  • 0%
    employees
Q.2.
What are two alternative names for​ process-focused facilities?
  • 100%
    intermittent and job shop facilities
  • 0%
    input output control
  • 0%
    FCFS within a priority class
  • 0%
    Gantt schedule chart
Q.3.
Which of the following priority rules minimizes maximum​ tardiness?
  • 0%
    maximize WIP
  • 0%
    EDD
  • 100%
    SPT
  • 0%
    backward scheduling
Q.4.
Which of the following priority rules minimizes the average number of jobs in the​ system?
  • 100%
    SPT
  • 0%
    EDD
  • 0%
    maximize WIP
  • 0%
    backward scheduling
Q.5.
Cycling scheduling is usually used for scheduling
  • 0%
    finite planning
  • 0%
    customer demands
  • 0%
    routing
  • 100%
    employees
Q.6.
Which of the following rules does a​ hospital's emergency room usually use for treating​ patients?
  • 100%
    FCFS within a priority class
  • 0%
    backward scheduling
  • 0%
    finite planning
  • 0%
    maximize WIP
Q.7.
What is a technique used to monitor jobs in​ progress?
  • 100%
    Gantt schedule chart
  • 0%
    input output control
  • 0%
    master schedule
  • 0%
    cyclical scheduling
Q.8.
Which of the following statements is NOT true about​ process-focused facilities?
  • 0%
    Process-focused facilities are common in​ high-variety, high-volume manufacturing.
  • 0%
    backward scheduling
  • 0%
    FCFS within a priority class
  • 100%
    Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
Q.9.
Which of the following is NOT a​ process-focused facility?
  • 0%
    FCFS within a priority class
  • 0%
    motorcycle assembly line
  • 0%
    master schedule
  • 0%
    backward scheduling
Q.10.
Which of the following is NOT an alternative name for finite capacity​ scheduling?
  • 0%
    maximize WIP
  • 0%
    finite planning
  • 0%
    Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
  • 0%
    master schedule
Q.11.
Which of the following statements is NOT true regarding finite capacity​ scheduling?
  • 0%
    finite planning
  • 0%
    Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
  • 0%
    Process-focused facilities are common in​ high-variety, high-volume manufacturing.
  • 0%
    maximize WIP
Q.12.
Which of the following is NOT one of the criteria used to evaluate scheduling​ performance?
  • 100%
    master schedule
  • 0%
    maximize WIP
  • 0%
    finite planning
  • 0%
    backward scheduling
Q.13.
Loading
  • 100%
    is the process of assigning jobs to work or processing centers.
  • 0%
    intermittent and job shop facilities
  • 0%
    Process-focused facilities are common in​ high-variety, high-volume manufacturing.
  • 0%
    Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.