Ch. 15 Short Term Scheduling Quiz
Solution
MCQ Questions
Q.1.
The sequence of work for a job is also known as its
0%
finite planning
0%
input output control
100%
routing
0%
employees
Q.2.
What are two alternative names for process-focused facilities?
100%
intermittent and job shop facilities
0%
input output control
0%
FCFS within a priority class
0%
Gantt schedule chart
Q.3.
Which of the following priority rules minimizes maximum tardiness?
0%
maximize WIP
0%
EDD
100%
SPT
0%
backward scheduling
Q.4.
Which of the following priority rules minimizes the average number of jobs in the system?
100%
SPT
0%
EDD
0%
maximize WIP
0%
backward scheduling
Q.5.
Cycling scheduling is usually used for scheduling
0%
finite planning
0%
customer demands
0%
routing
100%
employees
Q.6.
Which of the following rules does a hospital's emergency room usually use for treating patients?
100%
FCFS within a priority class
0%
backward scheduling
0%
finite planning
0%
maximize WIP
Q.7.
What is a technique used to monitor jobs in progress?
100%
Gantt schedule chart
0%
input output control
0%
master schedule
0%
cyclical scheduling
Q.8.
Which of the following statements is NOT true about process-focused facilities?
0%
Process-focused facilities are common in high-variety, high-volume manufacturing.
0%
backward scheduling
0%
FCFS within a priority class
100%
Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
Q.9.
Which of the following is NOT a process-focused facility?
0%
FCFS within a priority class
0%
motorcycle assembly line
0%
master schedule
0%
backward scheduling
Q.10.
Which of the following is NOT an alternative name for finite capacity scheduling?
0%
maximize WIP
0%
finite planning
0%
Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
0%
master schedule
Q.11.
Which of the following statements is NOT true regarding finite capacity scheduling?
0%
finite planning
0%
Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.
0%
Process-focused facilities are common in high-variety, high-volume manufacturing.
0%
maximize WIP
Q.12.
Which of the following is NOT one of the criteria used to evaluate scheduling performance?
100%
master schedule
0%
maximize WIP
0%
finite planning
0%
backward scheduling
Q.13.
Loading
100%
is the process of assigning jobs to work or processing centers.
0%
intermittent and job shop facilities
0%
Process-focused facilities are common in high-variety, high-volume manufacturing.
0%
Finite capacity scheduling directs delivery requirements to be based on a set of predefined rules.