PERT analysis computes the variance of the total project completion time as:
100%
The sum of the variances of all activities on the critical path.
0%
Planning, scheduling, and controlling
0%
Only critical activities contribute to the project variances.
0%
are used when two activities have identical starting and ending events.
Q.2.
An activity on a PERT network has these time estimates: optimistic =2, most likely = 3, and pessimisticIts expected time and variance (if it is a critical activity) are:
0%
Slack time
0%
3.67 and 1
0%
19 days
0%
Early Start
Q.3.
An activity has an optimistic time of 15 days, a most likely time of 18 days, and a pessimistic time of 27 days. What is the expected time?
0%
3.67 and 1
0%
19 days
100%
Early Start
0%
Slack time
Q.4.
With respect to PERT and CPM, slack__________
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
because near-critical paths could become critical paths with small delays in these activities
Q.5.
The Beta distribution is used in project management to
0%
longest time path through the network
0%
No activity in the network must be repeated.
0%
calculate expected activity times
0%
Planning, scheduling, and controlling
Q.6.
The three phases involved in the management of large projects are:
0%
longest time path through the network
0%
Planning, scheduling, and controlling
0%
calculate expected activity times
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
Q.7.
__________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
0%
3.67 and 1
0%
19 days
0%
Slack time
0%
Early Start
Q.8.
An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic time of 23 days. What is its variance?
0%
5.33
100%
4
0%
1.22
0%
2.33
Q.9.
In a PERT network, non-critical activities that have little slack need to be monitored closely__________
0%
because near-critical paths could become critical paths with small delays in these activities
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
Q.10.
The EF of an activity is the:
0%
No activity in the network must be repeated.
0%
Early Start
0%
ES + Activity Time
0%
longest time path through the network
Q.11.
A project's critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
0%
2.33
0%
4
0%
1.22
0%
5.33
Q.12.
Dummy activities__________
0%
The sum of the variances of all activities on the critical path.
0%
is the amount of time a task may be delayed without changing the overall project completion time.
0%
are used when two activities have identical starting and ending events.
0%
because near-critical paths could become critical paths with small delays in these activities
Q.13.
Which of the following statements regarding PERT analysis is true?
0%
Only critical activities contribute to the project variances.
0%
Early Start
0%
Gantt charts are visual devices that show the duration of activities in a project.
0%
No activity in the network must be repeated.
Q.14.
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, how many networks are in this path?
0%
Planning, scheduling, and controlling
0%
There are four paths in the network.
0%
Work Breakdown Structure
100%
calculate expected activity times
Support mcqgeeks.com by disabling your adblocker.
Please disable the adBlock and continue. Thank you.